060 GI 250 F064601C 060-D-(227)T PHOENIX-GLOBE HIGHWAY (US 60) (W Santee St to US 70)
SouthEast DistrictItem # 103679
Engineering Specialist: Mahdi Ghalib
Pre-Qualification: YES
Bid Opening: 5/23/2025 11:00:00 AM
System Preservation (Engineering)
The proposed project is located in Gila County on US 60 beginning at Milepost 250.00 and ending at Milepost 252.05. The work consists of pavement rehabilitation and addressing ADA compliance. The work consists of milling the existing asphaltic concrete and replacing it with new asphaltic concrete, furnishing and installing aggregate base and asphaltic concrete; curb and gutter; sidewalks; guardrail; bridge deck seals; striping; signing; signal pushbuttons; and other related work.
Bid Amount |
Contractor Name |
Contractor Address |
$5,176,133.00
|
DEPARTMENT |
PHOENIX, AZ |
$4,689,300.00
|
GRANITE CONSTRUCTION COMPANY |
TUCSON, AZ |
$5,405,941.12
|
COMBS CONSTRUCTION COMPANY, INC. |
GLENDALE, AZ |