Project Detail

0000 GI GGI T008701C GGI-0-(215)T GILA COUNTY, GORDON CANYON CREEK (COLCORD RD BR 11465 - .8M WEST)
NorthCent DistrictItem # LOCAL
Engineering Specialist: Patwary Mohammed
Pre-Qualification: YES
Bid Opening: 1/31/2020 11:00:00 AM

System Preservation (Bridge Replacement)

The proposed project is located in Gila County, approximately 3.3 miles east of milepost 277.24 on State Route 260. The work consists of constructing a new single span bridge using Accelerated Bridge Construction methods with Prefabricated Bridge Elements (PBE) and related roadway and drainage improvements on Colcord Road over Gordon Canyon Creek. Additional work includes removal of an existing culvert crossing, grading of an existing dirt road to be used as a detour, and construction of a concrete ford crossing of Gordon Canyon Creek.
Plans Cost
Bid Set$1.00
Spec SetN/A
Earth WorkN/A
Cross SectionN/A

Last Updated 1/21/2020 4:04 AM