Project Detail

073 GI 324 F011701C 073-A-(206)T CARRIZO-WHITE RIVER-INDIAN PINE, SR 73 (W OF RIM TANK - W OF CANYON DA)
NorthEast DistrictItem # 7871
Engineering Specialist: Layth Al Obaidi
Pre-Qualification: YES
Bid Opening: 1/31/2020 11:00:00 AM

System Preservation (Restoration/Rehab/Resurface)

The proposed work is located in Gila County on State Route 73 from milepost 330 to milepost 324, approximately 6 miles west of Fort Apache. The proposed work consists of milling the existing pavement and replacing it with asphaltic concrete and a chip seal coat. Additional work includes extending pipe culverts, placing gabions and slope mattress riprap, replacing pavement markings, and other related work.
Plans Cost
Bid Set$1.00
Spec SetN/A
Earth WorkN/A
Cross SectionN/A

Last Updated 1/21/2020 4:04 AM