Project Detail

017 YV 269 F061601C 017-B-(239)T CORDES JUNCTION - FLAGSTAFF HIGHWAY (I-17) (E Dugas Road - MP 275)
NorthWest DistrictItem # 103770
Engineering Specialist: Vian Rashid
Pre-Qualification: YES
Bid Opening: 11/6/2026 11:00:00 AM

Superelevation Improvements

The proposed project is located on Southbound Interstate 17 (I-17) in Yavapai County and Prescott National Forest, north of the East Dugas Road Traffic Interchange at MP 269.3 and extending to MP 275.6. The work consists of superelevation improvements by reconstructing the southbound I-17 pavement through differential milling and new pavement to increase cross slopes of the road. The work includes asphaltic concrete milling and paving, concrete barriers, rock scaling, down drain and spillway replacement, erosion control, pavement markings, signing, and other related work.
Plans Cost
Bid SetN/A
Spec SetN/A
Earth WorkN/A
Cross SectionN/A

Last Updated 9/16/2026 1:38 AM