Project Detail

179 YV 304 F078301C 179-A-NFA RIMROCK-SEDONA HWY (Red Rock Ranger Station - Chap)
NorthCent DistrictItem #
Engineering Specialist: Mike Wechselberger
Pre-Qualification: YES
Bid Opening: 4/17/2026 11:00:00 AM

System Preservation (Restoration/Rehab/Resurface)

The proposed work is located in Yavapai County on SR 179 between mileposts 304.38 and 310.50 between Red Rock Ranger Station and Chapel Road near Village of Oak Creek. The proposed work consists of milling existing chip seal surface and applying two-pass micro-surfacing. The project also includes spot repair work by milling and replacing with asphaltic concrete. Additional work includes replacing pavement markings and other miscellaneous work.
Plans Cost
Bid SetN/A
Spec SetN/A
Earth WorkN/A
Cross SectionN/A

Last Updated 3/14/2026 12:13 PM